I'd like to explain to you about the Project Schedule.
First of all, Simple Cycle.
Simple Cycle is consist of two Gas Turbines and be related facilities.
We have made plan on the assumption that have an effect on the NTP on Augst 1st.
Main milestone plans are as follows
Fuel Gas and Raw Water will be supplied on Oct 26th, 2014
and High Voltage Power will be received on Nov first.
After finished precedence activities 1st Initial Firing will be begun on Nov 23rd and 2nd Initial Firing on Mar 23rd.
Gas Turbines are in progress of manufacture for punctual schedule of Symple Cycle.
Consequently we will bring them on to the site at the same time on Feb thirteenth.
We make a supposition that will be on going along the schedule.
We will expect that GT no.1 will be completed on Jan 31st and GT no.2 on May 31st.
The next is Combine Cycle.
Combie Cycle is consist of two HRSG, one Steam Turbine and Circulating Water System.
Main milestone plans are as follows
Steam admission will be begun on April 14th.
Synchronization of Steam Turbine will be complted on April 27th and Combine Cycle will be completed on July 31st.
The next is the Critical Path.
First, in case of Simple Cycle.
We're going to the site preparation works and pile test during a month from NTP.
We will execute the pile work both GT no.1 and Cental Control Building simultaneously.
Critical path of the Simple Cycle are not only installation of Gas Turbine but also construction of Cental Control Building.
In case of combine cycle.
Critical path is installation of major equipment such as HRSG and Steam Turbine.
After all of the installation works that will be executed consecutively steam blowing, restoration and commissioning works about the steam line.
This is end of explanation, thank you for listening.
Hi Jay!
Hope the modifications that have made will help you.
You are always welcome!
I'd like to explain to you about the Project Schedule.
First
of all, Simple Cycle.I would like to discuss about the Simple Cycle.Simple Cycle is consist of two
Gas Turbinesgas turbines andberelated facilities.We have made plan on the assumption that it will have an effect on the NTP on
Augst 1st.August 1.Main
milestoneplans are as followsFuel
Gasgas andRaw Waterraw water will be supplied onOct 26th, 2014October 26,2014.and
High Voltage Powerhigh voltage power will be received onNov first.November 1.After the finished
precedenceprecedent activities, the1stInitialFiringinitial firing will bebegunonNov 23rdNovember 23 and2nd Initial Firingsecond firing onMar 23rd.March 23.Gas
Turbinesturbines are in progress ofmanufacturemanufacturingfor punctualin line for the schedule ofSymplethe Simple Cycle.Consequently, we will bring them
onto the site at the same time onFeb thirteenth.February 13.We make a supposition that it will be on going
alongexactly on the schedule.We will expect that GT no.1 will be completed on
Jan 31stJanuary 31 and GT no.2 on May 31st.The next is the Combine Cycle.
CombieCombine Cycle is consist of two HRSG, oneSsteamTturbine andCcirculatingWwaterSsystem.Main milestone plans are as follows:
Steam admission will
be begunbegin on April 14th.Synchronization of
SsteamTturbine will becompltedcompleted on April 27thand Combine Cycle will be completed on July 31st.The next is the Critical Path.
First, in case of Simple Cycle.
We're going to the site preparation works and pile test during a month from NTP.
We will execute the pile work both GT no.1 and
CentalCentral Control Building simultaneously.Critical path of the Simple Cycle are not only the installation of
GgasTturbine but also construction ofCentalCentral Control Building.In case of the combine cycle.
Critical path is installation of major equipment such as HRSG and Steam Turbine.
After all of the installation works,
thateverything will be executed consecutively the steam blowing,restorationrestoring and commissioning works about the steam line.This is end of explanation, thank you for listening.